‘Early funds release by Karnataka Govt will help speedy completion of works’, Kharge

Gulbarga: Railway Minister M. Mallikarjun Kharge said that if the Karnataka state government expedited the release of its share of Rs.800 crore for the railway projects taken up under cost-sharing basis, work would be completed quickly. Addressing a press conference at Gulbarga on Monday, Mr.Kharge said that for the past four months, the State government had not released any funds for the railway projects taken up on cost-sharing basis. He said that the State government should speed up the process of acquisition of land for four projects — Kottur-Harihar, Sakleshpur-Chikmagalur, Hassan-Bangalore and Kolar-Chickballapur. The early release of the State’s share of funds for the projects would help the Railways release its contribution of Rs. 800 crore, he said.

Kharge will lay foundation stone for a Rail Bridge across Bennithora River on Bidar-Gulbarga new Railway line on Tuesday at 02 00 PM at a function to be held at Community Hall, Mahagaon, Gulbarga. Several public representatives, dignitaries and senior railway official will be present on the occasion. The new BG line project was sanctioned in 1998-99 with an estimated cost of Rs 369.70 Crores. The total length of Railway track is 110.40 Km between Khanapur-Gulbarga Stations and 60 Km track has been linked/engine rolled by March, 2013 While the revised cost of the project is Rs. 792 Crores, an amount of Rs 383 Crores were spent till June 2013.

Salient features of the Railway Bridge Bennithora River as part of Bidar-Gulbarga New BG Railway Line Project

  1. The catchment area of the river is 2110 Sq Km
  2. Total Utilization of water is 5.75 TMC
  3. Length of stream 109.5 Km with Right bank canal 82Km length, Irrigable area 13435Ha
  4. Left bank canal 60Km length, irrigable area 6779Ha
  5. Benefitted Taluks – Sedam & Chittapur
  6. The new Bennithora River Rail Bridge is crossing the Bennithora River at about 2.00Km UP stream side of existing Road Bridge at Kurkotta Village
  7. The new Benithora River Rail Bridge is proposed at Km 76.560 in Bidar-Gulbarga New BG Railway Line Project between Kurkotta–Nawadgi Stations as 1X17.15M+14X18.0M+1X17.15M PSC Girders .
  8. Foundation is predominantly with Well foundations and Superstructure with PSC Girders
    (2 Girder System) with Deck Slab
  9. The estimated cost for the construction of Rail Bridge is Rs. 12.60 Crores
  10. The Bridge will have 16 spans, each with a length of 18.3 metres, spread over a total distance of 286 metres
  11. The targeted completion period is 18 months

Salient features of the Bidar-Gulbarga New BG Railway Line Project

  1. New BG line project was sanctioned in 1998-99 with an estimated cost of 369.70 Crores
  2. Total length of Railway track is 110.40 Km between Khanapur-Gulbarga Stations
  3. 60 Km track has been linked/engine rolled by March, 2013
  4. The revised cost of the project is Rs. 792 Crores
  5. Total expenditure as o­n June, 2013 is Rs. 383 Crores
  6. Total Land requirement: 768.57 hecatre
  7. No. of New Railway Stations:12 Nos (7-Crossing, 5-Halt Stations)
  8. No. of Total Bridges – 256 Nos
  9. No. of Major water way Bridges – 12
  10. No. of Major Road Over Bridges/Road Under Bridges (ROBs/RUBs) for road traffic – 18
  11. No. of Minor water way Bridges – 183 Nos
  12. No. of Minor ROBs/RUBs for road traffic – 43 Nos
  13. Manned Level Crossings – 15 (11 Level Crossings are planned for elimination through construction of RUBs)
  14. Ruling gradient – 1 in 100 (C )
  15. Max. Degree of curvature – 2.50 Degree
  16. Total length of Margutti Tunnel – 1.50 Kms
  17. Max. Height of Bank – 24.40 m
  18. Max. Height of Cutting – 19.91 m