PM & Sonia lands in J&K to inaugurate Banihal-Qazigund Snow Sojourn Rail Project

14-Twitter-attack-IndiaInk-blog480A costly infrastructure build up to ferry the Snow Sojourn in J&K is being inaugurated today amid a situation wherein India mourns with not less than 10,000 citizens and pilgrims in Uttarakhand were killed in floods within the last one week, 10 young Indian Army Jawans killed in Srinagar within last 2 days, and another 9 young IAF Officers and Jawans killed in a Chopper crash while in rescue operations to airlift the stranded civilians in the flood affected hilly region of Uttarakhand, leave alone the struggles of bureaucracy struggling hard to manage the turmoil.  Interestingly, the apathy of the leaders is evident from the fact that a senior Defence Officer cited saying “Why are the Gods against us?” in the wake of these tragic incidents suggests diminishing levels of morale among our soldiers.
train_jpg_1498081gThe Banihal-Qazigund tunnel being inaugurated by PM Mr.Manmohan Singh is a project within Kashmir, not connecting to country’s main railway network – an uneconomical project ran in crores, at the cost of the nation.  However, Prime Minister Mr.Manmohan Singh and Congress President Ms.Sonia Gandhi landed in J&K yesterday amid the turmoils the country is facing only to “successfully inaugurate” the so called Snow Sojourn with Banihal-Qazigund Rail tunnel opened up in J&K connecting Kashmir with Jammu region, despite the fact that only 3 months ago, this ambitious railway project was described by the CAG as a link “only within Kashmir, rather than to Kashmir” which will still not connect the Kashmir valley with the rest of the country.
E39EB07D463924F8F5F6B1215EA6AC

The difference made by the tunnel is limited, says CAG – the 145 km railway track in Kashmir, crossing the Pir Panjal range, has finally touched the Jammu region. It has however done so in a small town called Banihal, which in the 2001 census had a population of less than 3,000. The remaining 142 km of track connecting Banihal to Udhampur is nowhere near completion.

Bad-weather-hits-rescue-operations-in-UttarakhandThough the Kashmir half of the project, most of which is on the flat surface of the valley, has been executed in 11 years, the Jammu part, running through a treacherous mountainous terrain, has been bedeviled by “poor planning” which, according to the CAG, caused losses to the tune of Rs 3,258 crores.

“The more critical section of the project between Katra and Banihal (117 kms) has been progressed only up to 12 to 14 per cent, and as complexities unfold during execution, the final cost of the project may rise manifold,” the CAG said, in its report released in March.
uttarakhandIn the project outlay of Rs 19,565 crores, the Kashmir part was estimated to cost Rs 5,340 crores while the corresponding estimate for the Jammu part was almost three times higher at Rs 14,225 crores.

The problems holding back the Jammu half of the project launched in 2002 arose largely from the flawed plan of skirting the landslide-prone Himalayas on the mountain slopes. This is a far cry from the Kashmir half of the project, where a 11 km tunnel has been built to cross the Pir Panjal barrier, insulating the track from the vagaries of nature.

kashmir_fullFor the more difficult terrain in the Jammu region, the Railways should have carried out a detailed survey of the area before deciding on the alignment, the CAG said. “This alignment passes through various thrust areas and fault lines in the Himalayas making the line vulnerable to seismic disasters. However, the Railways failed to carry out geo-technical investigations of the proposed alignment in a hitherto unexplored territory and relied entirely on aerial maps and satellite imagery.”

When questioned by the CAG, the Railways replied that they pursued investigation and construction simultaneously for achieving “quick visibility of progress of work”. The CAG report observed that the Railways were however silent on the implications of following “a high-risk strategy with a high probability of becoming counter-productive”. This indicated “total disregard of professional norms and inability of the Railway Board in enforcing compliance with the standards laid down in the engineering code.”

news_8_6_2013_6This project has also been the subject of a PIL filed by advocate Prashant Bhushan before the Delhi high court. On May 8, it issued a notice to the Railways on the petition seeking a review of the Jammu part of the project by an independent committee of experts. This was because, as the high court said in its 2010 verdict, the board’s own review was found to have been “scuttled” by two of its members, preventing consideration of a better alternative. The board is due to file its reply by the next hearing on July 24.